Land in Rock garden, Yapral

Soil testing - 1

Soil Testing - 2

Level station survey

Borewell digging

Digging pits

Plain concrete cement (m10, 140+90)

Column placement (tata steel fe 500 d)

Anti-termite treatment - 1

Concrete for footings M25 (250+90)

Concrete for pedestals m25 (250+90)

Column laying M25 (250+90)

Plinth beam construction

Plinth beam Concrete filling

Anti termite treatment at Plinth level

SUMp digging and construction

Plinth bed

Slab - 1 construction

Slab - 1 RMC M25 (250+90)

Slab - 2 RMC M25 (250+90)

Slab - 3 RMC M25 (250+90)

Birla Aerocon Blocks marking

Sil level construction (Bond beam & Doors)